I just reviewed our start date and can’t believe we have been pressing on now for 61 weeks. This week will start week 62 which has some very exciting activities planned, but let’s not get too far ahead.
Here is what has been happening lately.
- Kitchen south wall cabinet bases constructed (including double oven)
- Poured and polished our first concrete kitchen countertops
- Spiral stairs are in, yeah!!!
- All recessed lights installed in the apartment
- House half-bath finished
There is a lot more happening, so more updates soon.